Nine installation procedures of aluminum extrusion press

Release date:2017-12-27 Author:铝型材挤压机的九大安装程序 Click:

Have a great relationship with aluminum extrusion level of efficiency and service life of the machine and the length of aluminum extrusion machine installation sequence, general equipment based extrusion machine, in addition to the weight of the material can withstand the weight and the production equipment itself, but also bear the dynamic load effect of extrusion machine work, so the aluminum extrusion machine equipment installation the installation must be carried out in accordance with the corresponding program.

1, the foundation pit is dug out according to the requirements of the equipment instructions, and the wire pipe is excavated, the upper and lower pipe and the compressed air pipe are used.

2, according to the extrusion of anchor bolt hole size distance, fixed anchor hole pattern. The anchor hole pattern should be a ladder or on the lower cone.

3, for the first time, the foundation is irrigated and the foot hole is left. On the basis of cover bags, 24 hours a day water two times health. The environment temperature should be above 5 centigrade.

4, after seven days of cement based maintenance, remove the template of the foot hole, hoist the extruder and place it on the foot hole position, and roughly find the height, horizontal and center line location.

5, the anchor bolt for each hole equipment fastening bolts through the connecting hole equipment, screw nut. Pay attention to the length of the thread adjustment.

6, irrigate the foot hole, fixed bolt, health maintenance period should be more than ten days.

7, a pair of diagonal iron (inclined 1/10~1/20) and a flat steel plate are used as a group. Under the flat plate, a pair of diagonal iron is skew and opposite on the plate, and the cushion is on both sides of the anchor bolt hole, and the horizontal height is adjusted by using the skew iron. At the same time, the center line of the extrusion machine coincides with the center line of the extruder production line.

8, pre tightened anchor bolts, to the corner pre tightening of the nuts, tightening force should be consistent.

9, correct the equipment level, center height and center line, fasten the bolts all over the world, connect the water, the trachea road and connect the electrical circuit.

It should be noted that after the installation of aluminum extrusion press, the process technicians must read the equipment instructions carefully, and formulate the trial production process of plastic products, commissioning operation procedures, material plan and commissioning tools and commissioning time according to the requirements of the instructions. Understand and familiarity with the function of the equipment structure and parts, and memorize the functions of each button and switch function.